Timeline
| Dates | Milestone | Complete |
|---|---|---|
|
January 2006 |
*Draft Project Initiation Document submitted | Yes |
| February 2006 | *Gateway 0 Review undertaken | Yes |
|
March 2006 |
*Final Project Initiation Document submitted | Yes |
|
November 2006 |
*Strategic Business Case submitted | Yes |
| February 2007 |
*Strategic Business Case approved by DfES |
Yes Yes |
| March 2007 |
*Gateway 1 Review undertaken |
Yes Yes |
| April 2007 | *Commencement of ICT contract tendering | Yes |
| July 2007 |
*Outline Business Case approval from Partnerships for Schools |
Yes Yes |
| September 2007 | *Commencement of Design and Build contract tendering *Bidders’ Day 3rd September |
Yes Yes |
| October 2007 | *Shortlist ICT contractors *Shortlist Design and Build contractors |
Yes Yes |
|
February 2008 |
*Selection of preferred ICT bidder | Yes |
| February 2008 |
*D&B bids received *Planning consultation for Acklam Grange and Ormesby |
Yes Yes |
| April 2008 |
*Award of ICT contract |
Yes |
| May 2008 |
*ICT Final Business case submitted *D&B preferred contractor selected |
Yes Yes |
| June 2008 | *ICT contractor announced | Yes |
| July 2008 |
*New Catholic School named as Trinity Catholic College *Planning application submitted for Ormesby-Priory Woods Schools |
Yes Yes |
| August 2008 |
*Design and Build Final Business Case submitted |
Yes |
| September 2008 |
*Planning application for Ormesby-Priory Woods Schools approved *ICT Final Business case approved |
Yes Yes |
| November 2008 |
*Acklam Grange planning approval *ICT contract signed *Design and Build Final Business Case approved |
Yes Yes Yes Yes |
| December 2008 |
*Second BSF Student Conference *Design and Build contract signed |
Yes Yes |
| January 2009 |
*Start on site ceremony at Acklam Grange |
Yes |
| February 2009 | *Commencement of construction of Ormesby and Priory Woods | Yes |